Five-Month Shutdown Ends for Portland Filtration Plant Project
Construction crews will return to work June 30th to meet a hard federally mandated Sept. 2027 deadline for Portland, Ore. to filter its drinking water.
After substantial site work had been done on an early phase of the project, the Oregon Land Use Board of Appeals stopped the work in January on the city’s Bull Run Filtration Project in East Multnomah County, Ore., by requiring the county to re-evaluate its approval.
A county hearing officer finally gave the project the green light, the city announced June 25th.
The pause in the land-use process “has been costly for the project and customers,” the city said in a statement. The delay “placed at risk the nearly one million people who rely on safe, reliable drinking water.”
Mayor Keith Wilson added that “the city is eager to put hundreds of construction tradespeople back to work to complete these critical water system improvements.” The city indicated that the work will involve excavation and concrete placement.
When completed, the project’s two parts, the filtration plant and a pipeline, will deliver raw water from the Bull Run River to the new filtration facility and then treated water to residents. Selection of contractor teams by the Portland City Council in 2023 set in motion in what is now estimated to be a total $2.1 billion worth of work.
The filtration facility is being built by MWH Constructors and Kiewit Corp as the construction manager/general contractor. Brown and Caldwell, Stantec and Carollo Engineers are also part of the team. The large-diameter pipeline project is a joint venture of J.W. Fowler and MWH.
The ruling followed an appeal by local groups and residents, who argued the project’s environmental impacts were not fully evaluated. After considering the challenge, the land use appeals board decided Multnomah County had failed to fully consider natural resources in its decision approving construction and in January remanded the matter back to the county based on an inadequate definition of the phrase “natural resources.” Work at the site stopped on Feb. 14, 2025.
That set the stage for what came next.
A public hearing on April 16 drew 320 attendees.
Meanwhile, some state senators tried unsuccessfully to legislate away the land use appeals board’s authority on the issue. They proposed through a law that never passed that some land use changes move forward without appeal board approval if the Oregon Health Authority, Department of Environmental Quality or United States Environmental Protection Agency has established a deadline for the development of the facility.
According to the Portland Water Bureau, the county’s hearing officer did impose new conditions to protect and improve wildlife and water quality in a creek, but the officer said the project won’t harm any category of natural resource. The decision considers natural resources and concludes that the project will “not adversely affect any category of natural resource,” the water bureau stated.
The Bull Run Filtration Project, which will ultimately treat about 140 million gallons of water daily, is located 18 miles east of Portland near Mount Hood on a roughly 95-acre city-owned parcel.
Portland had a water treatment waiver in place until cryptosporidium, a naturally occurring parasite, was detected in 2017. That triggered the federal Safe Drinking Water Act mandate and led to revocation of Portland’s water treatment waiver. Filtration will also help remove suspended sediment and potentially cancer-causing chemicals.
According to its announcements, the Portland Water Bureau during the shutdown prioritized site maintenance to ensure a swift restart. Crews conducted stormwater management, erosion control and grading to stabilize excavations. Tunnel portals were braced and equipment maintained to be ready to go again. The primary access points to the jobsite were secured with round-the-clock patrols.